Construction iteration 1 is the third iteration in release 1 development. In combination with the upcoming elaboration iteration 2, it will lead to the Initial Operational Capacity (IOC) milestone and review, planned for February, 2011.

  • Design Period: Tuesday, Sept 7 - Sept 17, 2010
  • Development:  Monday, Sept 20 - Friday Oct 22
  • Wrap Up: Monday, Oct 25 - Friday, Oct 29

Goals and Tasks

  • See Construction period and IOC goals
  • Update CI Technology List (as GoogleDocs spreadsheet)

Architecture Development

  • Architecture Construction 1

Subsystem Integrated Product Teams (IPT)

Data Model Development

  • Data Model
  • Versioning, Provenance, and Related Concepts

System Implementation

Baseline Materials

  • CI Architecture

Meeting Notes

  •  