Basics

Construction iteration 2 is the second iteration in release 1 construction phase.

  • Design Period: Wednesday December 1 - Friday December 17 (2+ weeks)
  • Development: Monday December 20 - Friday February 4 (5 weeks - not including the two weeks of UCSD shutdown from December 20-December 31)
  • Wrap Up: Monday February 7 - Friday February 11 (1 week)

Design

Goals and Tasks

  • See Construction period and IOC goals
  • See [Design Period Activities]
  • Update CI Technology List (as GoogleDocs spreadsheet)

Iteration Wrap-up

Architecture Development

Subsystem Integrated Product Teams (IPT)

Other Teams on Independent Iterations:

System Implementation

Baseline Materials

CyberPop Construction