Basics

Elaboration iteration 3 is the first iteration in release 1 construction. In addition with the two previous elaboration iterations it will lead to the Life Cycle Architecture (LCA) milestone and review, planned for August, 2010.

  • Design Period: Monday June 21 - July 2
  • Development: Monday July 6 - Friday Aug ?
  • Wrap Up: Monday - Friday

Design

Goals and Tasks

Architecture Development

Subsystem Integrated Product Teams (IPT)

System Implementation

  • CyberPoP Elaboration 3
  • Instrument and Platform Agent Architecture (IPAA)
  • External Observatory Integration (IOOS)

Baseline Materials