Construction iteration 1 is the First of three iterations in the release 2 construction phase. This iteration will last 10 weeks.

  • Design Period: Monday March 26 - Friday April 20 (4 weeks)
  • Development: Monday April 23 - Friday May 25 (5 weeks)
  • Wrap Up: Monday May 28 - Friday June 1 (1 week)

Iteration Goals, Scope, and Tasks

Overarching Goals for Iteration

Release 2 is focused on initial Marine Implementing Organization capabilities, and the Construction 1 iteration is focused on completing a first set of functionality that will enable an end-to-end system to be launched and stress tested.

Subsystem Goals for Iteration

Subsystem Goals and Scope

Additional Resources

LCA Presentations

See: R2 LCA Presentations

Construction Kick-off

The Release 2 Construction Kick-off WebEx will be held on Friday April 13, at 9 AM Pacific Time.

Iteration Tasks

Architecture and Design Development

Subsystem Activities: Integrated Product Teams (IPT)

The iteration software development activities are organized by subsystem, or Integrated Product Teams. Visit the following pages to see an overview of each subsystem's goals for the iteration, and its planned tasks.

Click here to see goals and tasks

Application Integration

  • Architecture: [Release 2 integration]

System Implementation

Baseline Materials

Prototypes

The following prototypes were selected from the list of proposed Release 2 prototypes (see Prototyping). In this iteration, we will work on these prototypes. The architects and designs will provide high-level strategy and constraints and work with developers on defining prototype design and executing prototype goals.

Page: Indexing with ElasticSearch (CI Development) Labels: r2c1prototype, indexing
Page: Prototype CG-CI Common Driver (CI Development) Labels: r2c1prototype
Page: SciCDM Consolidation (CI Development) Labels: r2c1prototype, scicdm
Enter labels to add to this page:
Please wait 
Looking for a label? Just start typing.