Construction Iteration 4 is the final construction for release 2. Codenamed 2.1, it is being developed over a single construction iteration. This iteration will last 10 weeks.

  • Design Period: Monday January 28 - Friday February 15 (3 weeks)
  • Development: Monday February 18 - Friday April 1 (6 weeks)
  • Wrap Up: Monday April 4 - Friday April 8 (1 week)

Iteration Goals, Scope, and Tasks

Overarching Goals for Iteration

R2C4 is focused on completing out functionality to support initial Marine Implementing Organization summer deployments. It will also incorporate changes asked for during the Release 2.0 beta testing.

Iteration Jira Burndown Charts

NOTE: Still Needs To Be Updated once Jira tasks are entered for iteration ...

Burndown Charts

Subsystem Goals for Iteration

Subsystem Goals and Scope

Additional Resources

Release 2.1 Presentations

The release 2.1 kick-off Webex was held on Monday January 14th.

Release 2.0 Construction Kick-off

The Release 2 Construction Kick-off WebEx will be held on Friday April 13, at 9 AM Pacific Time.

Iteration Tasks

Architecture and Design Development

  • [Architecture Construction 4]

Subsystem Activities: Integrated Product Teams (IPT)

The iteration software development activities are organized by subsystem, or Integrated Product Teams. Visit the following pages to see an overview of each subsystem's goals for the iteration, and its planned tasks.

Click here to see goals and tasks

Application Integration

  • Architecture: [Release 2 integration]

System Implementation

Baseline Materials

Prototypes

The following prototypes were selected from the list of proposed Release 2 prototypes (see Prototyping). In this iteration, we will work on these prototypes. The architects and designs will provide high-level strategy and constraints and work with developers on defining prototype design and executing prototype goals.

Page: Indexing with ElasticSearch (CI Development) Labels: r2c1prototype, indexing
Page: Prototype CG-CI Common Driver (CI Development) Labels: r2c1prototype
Page: SciCDM Consolidation (CI Development) Labels: r2c1prototype, scicdm