Iteration Jira Burndown Charts

Basics

Elaboration iteration 2 is the second of three iterations in the release 2 elaboration phase.

  • Design Period: Monday October 31 - Friday November 11 (2 weeks)
  • Development: Monday November 14 - Friday December 16 (5 weeks)
  • Wrap Up: Monday December 19 - Friday December 23 (1 week)

Elaboration Kick-Off Presentations

Release 2 Elaboration Kick-off WebEx was held on September 6th. The following presentations are availabe from that WebEx:

Iteration Wrap-up Presentation

  • TO BE ADDED

Goals and Tasks

Architecture and Design Development

  • [Architecture Elaboration 2]

Integrated Product Teams (IPT)

Application Integration

System Implementation

Baseline Materials

Prototypes

The following prototypes were selected from the list of proposed Release 2 prototypes (see Prototyping). In this iteration, we will work on these prototypes. The architects and designs will provide high-level strategy and constraints and work with developers on defining prototype design and executing prototype goals.

Page: Prototype Data Streaming (CI Development) Labels: r2e1prototype
Page: Prototype Direct Access (CI Development) Labels: r2e1prototype
Page: Prototype Integrated Governance (CI Development) Labels: r2e1prototype
Page: Prototype Integrated Policy Engine (CI Development) Labels: r2e1prototype
Page: Prototype Process Execution (CI Development) Labels: r2e1prototype
Page: Prototype Resource Lifecycle (CI Development) Labels: r2e1prototype
Page: Prototype visualization pipeline standalone (CI Development) Labels: r2e1prototype