Basics

In the Inception phase, we must show that the architecture makes sense and is in hand. (It is not necessary to show that we have a working system achieving that architecture.) The results must satisfy the deliverables required for the Life Cycle Objectives review, which is held immediately following Iteration 2.

The activities of Iteration 2 will involve close collaboration between developers and architects, and the architecture documents will be collaboratively updated to reflect the best known design information. Elements of the architecture that are targeted for implementation after Release 2 should be so identified.

Release 2 Inception Iteration 2

Iteration 2 is the second iteration of the Inception period. The two iterations of Inception lead to the Life Cycle Objectives (LCO) milestone review, scheduled for the week of Aug 22, 2010.

  • Design Period: Monday June 27, 2011 - Friday July 8
  • Development: Monday July 11 - Friday Aug 12, 2011
  • Wrap Up: Monday Aug 15, 2011 - Fri Aug 19, 2011

Goals and Tasks

  • [CI Release 2 Inception 2 Deliverables]
  • Revise CI Technology List (as GoogleDocs spreadsheet)
  • See Inception period and LCO goals

Architecture Development

Integrated Product Teams (IPT)

Baseline Materials

Prototypes

The following prototypes were selected from the list of proposed Release 2 prototypes (see Prototyping). In this iteration, we will work on these prototypes. The architects and designs will provide high-level strategy and constraints and work with developers on defining prototype design and executing prototype goals.

Page: Prototype CI-SIAM on embedded platform (CI Development) Labels: r2i2prototype
Page: Prototype common object model implementation improvement (CI Development) Labels: r2i2prototype
Page: Prototype embedded platform software deployment (CI Development) Labels: r2i2prototype
Page: Prototype gevent based Python Capability Container (CI Development) Labels: r2i2prototype
Page: Prototype Governance (CI Development) Labels: r2i2prototype
Page: Prototype Instrument Life cycle (CI Development) Labels: r2i2prototype
Page: Prototype licensing solutions to run Matlab (CI Development) Labels: r2i2prototype

Workshops

The following workshops were selected from the list of proposed Release 2 workshops (see Workshop Proposal Summary and Workshop Proposal Analysis):

Page: Workshop on Data Product Generation and Versioning (CI Development) Labels: r2-workshop-proposal, r2-workshop-proposal-sa, r2-workshop-proposal-dm, r2i2workshop
Page: Workshop on GridFields and Scientific Data Modeling (CI Development) Labels: r2i2workshop
Page: Workshop Proposal on CEI and DM integration (CI Development) Labels: r2-workshop-proposal, r2-workshop-proposal-dm, r2-workshop-proposal-cei, r2i2workshop
Page: Workshop Proposal on how to develop ION services with COI components (CI Development) Labels: r2-workshop-proposal, r2-workshop-proposal-coi, r2i2workshop
Page: Workshop Proposal on Resource Life-Cycle Management (CI Development) Labels: r2-workshop-proposal, r2-workshop-proposal-coi, r2i2workshop
Page: Workshop Proposal on Scientific Feature Types Representation (CI Development) Labels: r2-workshop-proposal, r2-workshop-proposal-eoi, r2i2workshop
Page: Workshop Proposal on Visualization Framework (CI Development) Labels: r2-workshop-proposal, r2-workshop-proposal-as, r2i2workshop

Additional Design Materials

Enter labels to add to this page:
Please wait 
Looking for a label? Just start typing.