Skip to end of metadata
Go to start of metadata

Tuesday, August 30, 2011: Release 2 Product

The presentations are available (ordered by presenter) at the Index to R1 PRR and R2 LCO Presentations.
Time Topic Session Lead
08:00-08:30 TBD: Closed Review Board Session  
08:30-08:45 Welcome and Introductions John Orcutt, CI Principal Investigator
08:45-09:00 LCO/PRR Objectives and Format Frank Vernon, CI Deputy PI
  Technical Introduction  
09:00-09:30 Release 1 Overview Matthew Arrott, CI Project Manager
09:30-10:00 Release 2 Objectives and Schedule Matthew Arrott
10:00-10:15 Break

10:15-11:15 Release 2 Product Specification John Graybeal, CI Product Manager
11:15-12:15 Release 2 product description John Graybeal
12:15-13:15 Lunch (closed board meeting)

  Infrastructure Subsystems  
13:15-15:00 User Experience Susanne Jul, CI User Experience Lead
15:00-15:15 Break  
15:15-15:45
Risk Management
Alan Chave, CI System Engineer
15:45-16:00 Candidate Requirements Overview Alan Chave
16:00- Closed Review Board Session  

Wednesday, August 31, 2011: Release 2 Architecture

Group 1 of the parallel sessions focuses on infrastructure and CyberPoP/network designs. Group 2 focuses on application and agent designs.

Time Topic Lead
08:00-08:30 Review of Open Questions  
08:30-09:00 Architecture Overview Michael Meisinger, CI Senior System Architect
09:00-10:30 Parallel Sessions #1  
  Group 1: Common Operating Infrastructure Subsystem Stephen Henrie, COI Architect
  Group 2: Data Management Subsystem Maurice Manning, DM Architect
10:30-10:45 Break  
10:45-12:15 Parallel Sessions #2  
  Group 1: Common Execution Infrastructure Subsystem Kate Keahey, CEI Lead
  Group 2: Sensing and Acquisition Subsystem; OOI Science Data Products
Maurice Manning, SA Architect
12:15-13:15 Lunch (Review Board meets at their option)  
13:30-14:30 Parallel Session #3  
  Group 1: CyberPoPs and Network (Build 2) Mark James, Operations Manager
  Group 2: Marine Integration, Sensor Sets, and Dataset Agents Maurice Manning, SA Architect
14:30-15:00 Break  
15:00-15:30 Elaboration Phase Plan John Graybeal and Tim Ampe
15:30-16:30 Release 1 Demo Tim Ampe
16:30-17:00 Life Cycle Objective Wrap-up Alan Chave
17:00- Closed Review Board Session  

Thursday, September 1, 2011

Time Topic Lead
08:30-11:00 Release 1 Product Readiness Review/Integration & Validation Review  
08:30-11:00 LCO Closed Review Board Session at discretion of chair  
11:00-12:00 Release 2 Life Cycle Objective Review Board report out  